 Chianjhen Fish-Harbor dredging Project

Project Location:

South

Contract Price:

NT$427,680,000

Project duration:

600 calendar days from the c

Estimate completion date:

2025-02-28

Client:

Fisheries Administration, Council of Agriculture

Project Overview

The scope of this project is mainly the dredging of the channel, mats, and harbor basin in the southern half of Chianjhen Fishing Port. The dredged sediment will be disposed of in the form of ocean disposal after garbage cleaning. The dredged water area is about 13.445 hectares. The construction content is as follows:
(1) Quantity of dredging, workboat dredging and earthwork disposal at sea: the contractual design quantity is about 195,185m3, and it is 253,740m3 after evaluating 30% loose volume.
(2) Quantity of sundries sorted and disposed of (legal storage places), within 10km of transport distance: the total quantity is about 3,767 metric tons.