Services

 Air Force H007 Project

Project Location:

East

Contract Price:

NT$3,172,599,996

Project duration:

1795 day

Estimate completion date:

2027-08-07

Client:

Ministry of Defense

Project Overview

The scope of work includes the general site preparation of the base, construction water and electricity, the main body of the structure (including foundation, structure, etc.), landscape, roads, drainage, civil engineering, necessary geological improvement, water conservation facilities, demolition and transportation of existing camps on the base , air-conditioning equipment, power telecommunications and general lighting equipment, indoor and outdoor water supply, drainage, sanitation, fire-fighting equipment, statutory air defense refuge equipment, doors and windows, painting and interior decoration, etc.
The design scope includes civil engineering, structure, construction engineering (including foundation), landscape, road, drainage, necessary geological improvement, water conservation facilities, demolition and transportation of existing camps, water supply and drainage systems, power supply systems, building weak current systems, and electrical equipment , fire-fighting equipment, air-conditioning equipment and other public facilities (including sewage treatment, surrounding roads, surrounding drainage, street lighting equipment, etc.).